It’s been 3 weeks since we had an update (I tried last weekend, but I was locked out) but here’s the latest walkthrough of the dojo remodel!  

Loading

Read More

Happy New Year!!

Loading

Read More

Post Christmas Walkthrough

Greetings everybody, Happy holidays. For your viewing pleasure is our post Christmas remodel walkthrough.  Enjoy!    

Loading

Read More

Remodel progress

Post Image

Greetings again members, friends, and family! I made another stop at the dojo this week. The painting is, for the most part, done. They were bringing in wall coverings for the back bathroom as well as tearing up the old linoleum that was underneath the old tatami. The big change I noticed is that we […]

Loading

Read More

December Checkin

Post Image

Greetings again members, friends, and family! I made another stop at the dojo during my holiday outings. The day I came in, they were preparing the walls to be textured (before painting). If you look at the prior pictures, the walls look a little different. Planning a trip down to see how the painting went! […]

Loading

Read More

Holiday remodel checkin!

Post Image

Greetings again members, friends, and family of EBJI! Apologies for the delay since the last update. I actually took some pictures last week, but they didn’t come out. Not sure why, but I took several pics and only a couple of them weren’t blurry! Nonetheless, I dropped in today to check the progress before the […]

Loading

Read More

3.5 months checkin

Post Image

Greetings again members, friends, and family of EBJI! We’re now 3.5 months into the remodel and progress is pushing forward. The walls are all up and covered, the old electrical stuff is mostly removed and the new wiring is almost completely in place. All the concrete has now been poured, the extra support studs are […]

Loading

Read More

Remodel – 3 Months Checkin

Post Image

Greetings again members, friends, and family of EBJI! We’re 3 months into the remodel and progress continues. The walls are all up and almost completely covered. We can now see the shape we’re going to have. We’ve been informed that we’ve been given the OK to finally finish the concrete pour (the open holes you’ll […]

Loading

Read More

Remodel Week 10

Post Image

Greetings again to members, friends, and family of EBJI! It’s time for our Week 10 update! It’s been over a week since I took these pictures. My computer crashed, so I had to wait until it was repaired to be able to send the update. The new walls are pretty much up, at least the […]

Loading

Read More

Remodel Week 9

Post Image

Greetings again to members, friends, and family of EBJI! It’s week 9 and we’re deep into construction! Finally we have some pictures that aren’t primarily of demolition and preparation! Our front entryway. It’s actually a slight ramp to allow wheelchair accessibility. This is front view of what used to be the entry to the office. […]

Loading

Read More